ClickUp Gantt currently relies on a single timeline (Start/Due), which limits real project tracking.
Problem
Many teams track:
• Planned Start / Finish (Start & Due dates)
• Actual Start / Finish (custom fields)
But:
• Only one timeline can be shown
• Custom date fields cannot drive Gantt bars
• Baselines are static and don’t support live comparison
Request
• Allow multiple date sets per task (planned, actual, etc.)
• Allow selecting which fields drive Gantt bars
• Allow overlay / dual timelines in the same row
• e.g. Planned (solid bar) vs Actual (overlay or patterned)
Why this matters
• Enables true planned vs actual tracking
• Removes workarounds and misuse of baselines
• Aligns with tools like MS Project / Primavera
Limitation of “Date done”
“Date done” should not be used as Actual Finish:
• It is a non-customizable field
• Tasks are often closed later than work is completed
• It does not reliably reflect real execution
* Teams need separate Actual Start / Actual Finish fields, and the ability to visualise them alongside planned dates