Non-human resources in ClickUp
S
Stefan Kinell
I miss a function to have non-human resources in ClickUp. In my case it would be computers with computing power that my projects depend upon. But I assume there are many other applications.
Let me explain my use case today
I have a project where I want to plan different steps, calculate what from the backlog I can bring into work before next release etc. I have several tasks where I typically do this:
a) I prepare data, that is a step of 16 h work assigned to me
b) the computer runs for 320 hours doing calculations. That is a task I want to assign to a computer, it is depending on a) being finished
c) when the data processing is done, I am using that data in the next step - a task of 24 h working for me, c) is depending on b) being finished
I work 8 hours a day, 5 days a week.
the computer works 24 hours a day, 7 days a week.
I have tried using guest users after being adviced this would be a solution from support. But I see no way of assigning individual working hours, only on a work space level. And the computer is not affected by hollidays or weekends, it works over the days off.
Therefore I would ask for a feature to be implemented where we can set up resources, that are non-human, and that we can define work schedule for these individuall. and that these resources then can be used to assigne tasks to.